Article Title | Bonefish Cove Island Restoration Project Update | Post Date | Posted on
Friday, December 5, 2025 | Rollup Image | | Body |
December 2025
For ease of discussion, the Project and its components have been divided into a northern section and a southern section. Each section is comprised of one island, one bird nesting mound, multiple oyster reefs, a submerged seagrass shelf and red mangrove habitat. The area between the north and south sections is being left open in its existing state.
North Section
The contractor is putting the finishing touches on the last portion of the rock wave break structure around the island and planted the interior of the island with over 10,000 red mangrove propagules second week of November.
South Section
The contractor continues delivering, stockpiling and grading sand in this section in order to form the oyster reefs, submerged seagrass shelf and island. As they continue to deliver sand and rocks over the next several weeks they will repeat the same process used to construct the north section.
Important Reminders - Working hours at the Bonefish Cove project site are Monday to Sunday from 5:00am to 7:00pm.
- Starting November 17, 2025, through May 1, 2026, barge traffic through the Intracoastal Waterway will be limited to weekends and holidays only, with no barge traffic Mondays through Fridays.
- Isolated instances of removal and delivery of construction equipment for maintenance, replacement, or demobilization by barge will be allowed.