2022 Comprehensive Plan Amendment Schedules
With the exception of the intake dates, all dates are tentative
Small Scale Amendment Rounds
Activity |
22-A |
22-A2 |
22-B |
22-B2 |
Pre-Application Meeting |
Prior to April 5, 2021 |
Prior to July 1, 2021 |
Prior to October 1, 2021 |
Prior to January 3, 2022 |
Traffic Study Intake |
April 5, 2021 |
July 1, 2021 |
October 1, 2021 |
January 3, 2022 |
FLUA Application Intake |
May 12, 2021 |
August 11, 2021 |
November 10, 2021 |
February 9, 2022 |
Zoning Application Intake |
by June 25, 2021 |
by September 24, 2021 |
by December 22, 2021 |
by March 25, 2022 |
Large Scale Amendment Intake
Activity |
22-A |
22-A2 |
22-B |
22-B2 |
Pre-Application Meeting |
Prior to April 5, 2021 |
-- |
Prior to October 1, 2021 |
-- |
Traffic Study Intake |
April 5, 2021 |
-- |
October 1, 2021 |
-- |
FLUA Application Intake |
May 12, 2021 |
-- |
November 10, 2021 |
-- |
PLC Public Hearing 1 |
August 13, 2021 |
November 12, 2021 |
February 11, 2022 |
May 13, 2022 |
PLC Public Hearing 2 |
September 10, 2021 |
December 10, 2021 |
March 11, 2022 |
June 10, 2022 |
PLC Public Hearing 3 |
October 1, 2021 |
January 14, 2022 |
April 8, 2022 |
July 8, 2022 |
PLC Public Hearing 4
|
October 15, 2021 |
|
|
August 12, 2022 |
BCC Transmittal Hearing |
November 3, 2021 |
February 2, 2022 |
May 4, 2022 |
August 31, 2022 |
BCC Adoption Hearing |
February 2, 2022 |
May 4, 2022 |
August 31, 2022 |
November 28, 2022 |
Anticipated Effective Date |
March 2022 |
June 2022 |
September 2022 |
December 2022 |
For more information on proposed amendments visit the