As of Wednesday, February 28, 2024, two of the four separate repair locations with two pipes each to complete within the Pratt Whitney roadway have been replaced and are being prepared for restoration (shoulder, embankment, and roadway areas). During the pipe replacement the existing underground corrugated metal pipe (CMP) drainage pipes were in a state of failure. Currently, the projected eight week project duration still appears to be obtainable barring any weather or unforeseen circumstances.
We apologize for any inconvenience this may cause and thank the community for their patience and understanding as we complete these emergency drainage repairs as quickly and safely as possible.