Municipal Projects Update as of August 11, 2025

Post Date

Rollup Image

Municipal Projects Update as of August 11, 2025

Body

Gateway Blvd. & Military Trail

The existing span wires for the traffic signal have been modified to accommodate the lane re-alignment.  An additional southbound left-turn signal head and a northbound right turn 5-section cluster head have been added.  These will remain covered until the pavement work is completed.  The contractor is scheduled to begin the final paving work at the beginning of next month (September 2025).

Installation of the final traffic signal mast arms is currently being coordinated with FPL.  The area needs to be de-energized for the mast arm foundations to be installed and this is also currently scheduled for September.  The  custom mast arms have already been built and delivered.

To view all previous updates related to the Municipal Contractors' projects, please visit Engineering and Public Works Municipal Contractors Project Updates (pbc.gov). ​​​​