Gateway Blvd. & Military Trail
The existing span wires for the traffic signal have been modified to
accommodate the lane re-alignment. An additional southbound left-turn
signal head and a northbound right turn 5-section cluster head have been
added. These will remain covered until the pavement work is
completed. The contractor is scheduled to begin the final paving work at
the beginning of next month (September 2025).
Installation of the final traffic signal mast arms is currently being coordinated with FPL. The area needs to be de-energized for the mast arm foundations to be installed and this is also currently scheduled for September. The custom mast arms have already been built and delivered.