Article Title | Municipal Projects Update as of July 3, 2025 | Post Date | Posted on
Thursday, July 3, 2025 | Rollup Image | | Body |
Hypoluxo Rd. & Jog Rd. - Formwork installation is underway in preparation for concrete placement around pull boxes.
- Phase 1 work is complete, which included the signals at Cumberland farms, drainage repairs, curb and gutter, and milling and paving asphalt; awaiting confirmation of a final walkthrough date to close out this phase of the project.
- The roadway contractor is currently awaiting pricing from subcontractors for the Phase 2 concrete and asphalt work at the intersection of Hypoluxo and Jog.
- Concrete work for Phase 2 is expected to begin after the mast arms and bases are removed on the east side of the intersection.
- Pole/base removal is tentatively scheduled for mid-July, pending temporary FPL overhead electric line shutdown.
Gateway Blvd. & Military Trail - Concrete work and corner widenings have been completed, are operational, and open to pedestrian traffic
- Work was originally scheduled to begin May 12, but was delayed due to ongoing utility relocation work.
- Concrete crews mobilized on June 2 and completed all work by Friday, June 25th.
- Traffic signal heads are currently being realigned in preparation for milling and resurfacing operations.
- Contractors to begin Phase 2 concrete work in coordination with the paving schedule, allowing a single mobilization to complete concrete and milling/resurfacing work at both Gateway and Hypoluxo in sequence.
Subcontractor scheduling update: - Paving subcontractor currently has this project scheduled approximately 60 days out (around September 2nd) for nighttime work. The original paving schedule was based on earlier dates, but utility-related relocations forced the subcontractor to shift focus to other projects
Interim measure to minimize impacts to the public: - The subcontractor has proposed milling the asphalt drop-offs between the existing and new asphalt to minimize elevation differences. This would allow for the removal of MOT devices and the reopening of all lanes sooner.
- Temporary striping would be placed following milling.
- This work can be completed on a Saturday, minimizing traffic impacts during the work week
To view all previous updates related to the Municipal Contractors' projects, please visit Engineering and Public Works Municipal Contractors Project Updates (pbc.gov).
| | Attachments |
|
|