Article Title | Municipal Projects Update as of April 9, 2025 | Post Date | Posted on
Monday, April 14, 2025 | Rollup Image | | Body | Hypoluxo & Jog Project - Hypoluxo Rd west of Jog Road was milled and paved. The County is currently installing pavement markings and signage.
- The traffic signal on Hypoluxo Rd and Cumberland Farms is on flash mode today and message signs will be installed tomorrow to alert drivers about the upcoming signal activation.
- The county expects to have that signal operational on April 17th
- Staff is coordinating with FPL to de-energize power lines for 2 consecutive days to continue signal work at the intersection of Hypoluxo Rd and Jog Rd.
- County expects to install the signal drill shafts the week of April 21st and be able to install the mast arms at the beginning of May.
- After signal work, the next steps will be to complete milling and paving as well as complete sidewalk improvements.
Gateway & Military Project
| | Attachments |
|
|