Latest update for Municipal Projects as of 12/20/24:
There is still a significant amount of work remaining for the Hypoluxo Road/Jog Road and Gateway Blvd/Military Trail intersection improvement projects. After delays with the surety company, the County has decided to complete the projects internally to move them forward. The surety will reimburse the County for any additional costs incurred beyond the remaining project funds.
Following the removal of Municipal Contractors Inc. for nonperformance and failure to pay subcontractors, PBC Legal and Old Republic Surety Company (ORSCo) initially planned to rebid the work but faced further delays. As a result, the Engineering and Public Works Department (EPW) will use two of its annual contractors to finish the tasks as an emergency task order. These contractors will execute the remaining work, with pricing expected by late January.